SUDKABEL - Project- N-6526 - Yas Island

132 kV Cable Double Circuit Connection Between
The New 400/132kV G/S at BAHIA and The 132/22kV S/S at YAS ISLAND

The scope of work of this project comprises the route survey, identification of existing services / cables along the cable route, design, manufacture, transport, erection, installation, jointing, termination, testing, commissioning and handing over in satisfactory condition of the following power cable and fibre optical cable circuits including all accessories, related earth and civil works, and equipment necessary for the proper survey, installation, connection and operation. The entire Scope of Work/Scope of Supply consists of the following:

  • Two complete (3-phase) cable circuits of single core cross-linked polyethylene (XLPE) insulated cables 132kV, 1200 mm2 copper conductor
  • Two complete optical fibre cable with 144-fibres per circuit
October 17, 2012 - 132kV HV AC Cable Testing Activities
   
July 04, 2012 - PROGRESS OVERVIEW
   
1. SPAN No. 1 Circuit 1 & 2 – excavation works, cable laying, pipes laying for FOC and backfilling done. Cable laid inside the substation ,
GIS Termination works pending

2. SPAN No. 2 - 11. Circuit 1 & 2 – excavation works, cable laying, pipes laying for FOC, route marker fixing and backfilling done.


3. SPAN No. 12 Circuit 1 & 2 – under progress (HDD Ongoing)


4. SPAN No. 13 Circuit 1 & 2 – Cable Laying completed. Pipes laying for FOC completed.


5. SPAN No. 14 Circuit 1 & 2 under progress (NDRC works ongoing)


6. SPAN No. 15 Circuit 1 & 2 – Cable Laying completed. Pipes laying for FOC completed.


7. SPAN No. 16 & 17 Circuit 1 – Trench Excavation Cable Laying, FOC Pipe Laying completed.

May 05, 2012 - Span-13 Cable Laying

Cable Drum shifting

Cable spaceing

Joint pit marking

Jointpit-13 erection

Span-13 cable laying

Span-13 cable layed

Span-13 cable spacing

Span-13 Dune Sand filling

Span-13 roller assy
Novermber 2010 - N-6526 Project Sign Board
October 5, 2010 - Fixing of cable drum at cable jack and removal of cable drum cover
September 27, 2010 - Cable pulling at Span 06 inside green area at Yas Island
August 2010 - excavator rate 40 meter per day sp4 / the area for sp7
August 15, 2010 - 132KV CABLE AND FO PVC DRESSING & FIXING FOR SPAN NO 5 / CABLE LAYING FOR SPAN NO 9 FINISHED
July 2010 - duct at the position of joint SP.7 / New Container, Earthing Cable and Crossbonding Cable
May 27 2009
April 2009 - Preparation of cable pulling works with Project Manager Engr. Younis Shaaban

| Home | Policy | News | Services | Reference List | Location Map |
____________________________________________________________________________________________

REMCON ELECTRICAL - ABU DHABI - UAE
Silver Building, Al Dhafra St. (Street # 4) - Mezzanine Floor M1-M2
P.O. Box 29497 - Abu Dhabi. United Arab Emirates - Tel. No. +971-2-4458030 - Fax No. +971-2-4458035

REMCON ENGINEERING - SHARJAH -UAE
Phone +971 6 539 2281 - Fax No. +971 6 539 2282 - P.O. Box. 71265, Sharjah - United Arab Emirates

E-mail :info@remcon.ae